Will Walter C. Lyman's Dream Come True?

The tunnel started, stopped, and restarted many times. The biggest problem was finances, but a lot had to do with the attitude of the town and the workers. The tunnel was initiated around 1920, but was given up soon after because there was not money. It was revived again about 1940. This time they completed about 1400 feet before funds ran out. At this time, the Utah Power Board provided funds to help develop irrigation projects. The (Building a One Mile Long Tunnel) irrigation company applied for a loan of $75,000. The company wanted to buy out anyone who had stock in the tunnel through the mountain.

Vet Bradford in front of shop at the Blanding tunnel on Blue Mountain. Bradford kept the work going on both ends of the tunnel. - Donated to the San Juan Historical Society by Thora Bradford (Blanding, UT) in 1989.
 
Walter C. Lyman had taken Vet Bradford to the mountain and showed him the markers for the tunnel before his death in 1943. Lyman's son  Marvin wanted to see his father's dream of the tunnel being completed so he and Vet, and local construction workers, took out a contract to dig through. Because of hard rock and money, they were forced to give up for a while. However, they wanted to see it completed, so they later took out another contract to finish the tunnel. Both men put all the money they had into the project and financially were doing badly, while most of the people in Blanding were making more money than ever before. Most of the men working for them quit because they could make more money working somewhere else. The men who stayed did so because they wanted to help rather than get rich. Despite these problems, Bradford kept the work going on both ends of the tunnel. "Whenever I thought of the project, it seemed insurmountable, but I knew what would be accomplished was what was attempted and I concentrated on one day's work at a time." (Bradford and Winder 117) Marvin handled the finances while Vet and his crew built the tunnel.

Blasting Through the Tunnel

To get through the tunnel, they used both blasting and drilling. This is the procedure used.
"To blast through the tunnel, they went in with what was called a round. They drilled back in about six feet, then loaded the thing with powder, and when they were ready to shoot them, they shot the one they wanted to pull first because then the other ones would put to it. Then they would light the fuse and get out fast before it would go off. Then after they had gone off, they would have to wait several hours before they could go back in the tunnel to work."
 
South entrance of Blanding tunnel. On the right side of the tunnel is an air vent pipe that forced fresh air into the tunnel to clean out the smoke after the dynamite blasts. The shop is on the left side.  
- Kay and LaRae Bradford photo.
 
They finally put a pipeline in so they could blow air and blow the smoke out. After they did this, they could go back in the tunnel in about an hour. They had carts with railroad wheels that they would haul the rubble in and they dumped it in the dump.

Living Next Door to a Tunnel

In order for the tunnel to get finished, the men had to live on the site. While they were working on the ditch, they camped in a small trailer where there used to be a ranger station. When they worked on the tunnel, they built two or three cabins and lived there all the time. Often they did not even come down on weekends because of lack of transportation. (Black)

The Last Time and Finally . . . the Breakthrough

After the tunnel was worked on again for the last time, it took them about two years to get finished. With 4300 feet dug out the south sides and 1100 feet on the north side of the tunnel, they were very close to breaking through (A Christmas Present) . The two sides of the tunnel had passed each other by about two feet, so they could tell that they were close enough to each other that they just had to drill the two feet to meet. When it finally broke on December 27, 1951, there were many tears of joy. Cleal Bradford described it this way.
"Fifty years of thirst for their home folks and friends were ended, forty years of doubt and faith in the water being available, and thirty years of struggle to obtain it, the job was done." (Bradford and Winder 208.)

Not Finished Yet

As soon as possible in the spring of 1952, the men were back on the job. Some things had to be taken care of, such as relocating the ditch on the north side, before the water could be turned into the tunnel. On June 24, 1952, the water was turned into the hole in the mountain and was on its way to the mesa. (Palmer 2-6)

On June 24, 1952, they turned the water in from the north. Vet Bradford was crawling through the tunnel and had to get out the south side. He was upset because he didn't get to see the water go through, after he had diligently worked on the tunnel for so long. Ash Harris was president of the ditch company and was anxious to see the water go through the tunnel. He was not thinking about who was there and who wasn't when he turned it through.

The Irrigation Company owned 52 feet of water on the south side of the mountain. Whatever came through the tunnel they got. The city then bought two second feet of water on the north side of the tunnel after it was finished. This allowed Blanding to have the water that was available from the north side of the mountain. This gave the town enough water that it wasn't necessary for them to haul it.

The Blanding Tunnel is Worth the Sacrifice

Today Blanding's main source of water comes from the tunnel and the winter local water shed. In the spring thaw, it comes from the south side of the mountain and fills the 3rd and 4th reservoirs.
 
 
Left: Third Reservoir                                        Right: Fourth Reservoir looking east 
In the spring thaw, Blanding's main source of water comes from the south side of the mountain, goes through the tunnel, and fills the 3rd and 4th reservoirs. - Photo taken by Kristina Long, 1997.
 

There's also Johnson Creek which runs through all year round. The tunnel project took thirty years to complete. It was a little over 5,400 feet long and is reported to have cost $125,000. "There's been lots of money spent there, but its a nice stream of water that comes through there all the time. It's what saves this town," stated Frost Black. (Black)


Marcia Black is now attending Southern University of Utah. She completed this article as a junior at San Juan High School, Blanding, Utah, on February 1, 1991.


Works Cited:

Black, O. Frost. interviewed by Marcia Black, December 26, 1990.

Bradford, Cleal and Winder, Terri B. We'll Walk Through the Mountain, Shumway Family History Services, 1986.

Gregory, Herbert E. The San Juan County, United States Government Printing Office, Washington: 1938.

Lyman, Albert R. The Edge of the Cedars, Colton Press, New York.

Palmer, Preston The Blanding Tunnel Project, San Juan Collection, San Juan High School.

Perkins, Cornelia A. and Nielson, Marian. Saga of San Juan, San Juan County Daughters of Utah Pioneers, 1957.

 

Return to Table of Contents


Last Updated July 10, 1997 by Janet Wilcox