
Blanding's first
reservoir was built in 1916 just east of where the nursing home is
now. It wasn't big enough and a second reservoir
was built in 1920, just next to the water treatment plant. Both of these
reservoirs are no longer in use. (Shumway. 1-2) The third reservoir is
next to the third reservoir park. It holds 180 acre feet, but only 120
acre feet can be used. The other 60 is for fish conservation. The fourth
reservoir holds 580 acre feet and only 400 acre feet can be used. The other
180 acre feet are for fish conservation. (Palmer)
Water is Distributed by Rights
 |
Johnson Creek
is one of the creeks carrying water from Blanding
tunnel. - Photo taken by Kristina Long, 1997. |
Water is distributed by rights. Blanding City has one second foot right
in Johnson Creek and two second feet in Indian
Creek on the north side of the tunnel, purchased from Sommerville Cattle
Company for $10,000. (Perkins, Nielson, and Jones 163-164.) Water is measured
in second feet and acre feet. An acre foot is an acre foot of water, a
foot deep. There are 325,000 gallons in an acre foot. A second foot is
one cubic foot per second which is 1 foot by 1 foot. The flow of water
is measured by how many gallons flow in a minute. A second foot is 448
gallons a minute or a cubic foot per second. The city gets 1,344 gallons
a minute total plus 50,000 shares from Recapture Reservoir. (Palmer)
Repairing the Third and Fourth Reservoirs
The repair of the third and fourth reservoir took place during the summer
of 1990. The third was emptied and new pipes put in and the face of the
dam was covered with clay and a spillway was put in. There is some controversy
over this issue. The state seems to think that the city didn't do what
they should have done to fix the third but the city thinks they did. The
fourth reservoir was emptied and it was covered with clay. It took an estimated
60,000 tons of clay at a cost of $2.50 a ton. The cost of the clay was
$150,000. The total cost to fix the reservoir was just more than $300,00.
Johnson Creek
The Johnson Creek Well was drilled by Devon Hurst in 1962. It is 925 ft.
deep with 10 inch casing. It puts out about 100-120 gallons of water a
minute. The water is pumped by a propane motor which drives a shaft which
turns a gear box. This gear box turns a shaft down in the well about 500
feet. The shaft turns a pump which brings the water to the surface.
Storage Tanks, Starvation Reservoir, and Recapture
Dam
 |
| Blanding's storage tank above the ground. It is made out of cement
and holds one million gallons of water. It is 22 ft deep and has a diameter
of 45 feet. It was built by Hurst Construction in 1976. - Photo taken by
Kristina Long, 1997. |
Blanding has two water storage tanks. One is above ground and the other
is below. The one below is just at the foot of the knoll north of Blanding.
The one above ground is made out of cement and holds one million gallons.
It is 22 ft deep and has a diameter of 45 feet. It was built by Hurst Construction
in 1976. In 1985 Blanding built another reservoir called Starvation. It
cost 1.4 million dollars and holds 600 acre feet. There is no conservation
level requirement for this reservoir so all the water can be used. (Palmer.)
In 1982 Recapture Dam began to be built, but before it could be started,
an agreement had to be made with Ervin Guymon, a local farmer who owned
land where the dam was to be built. He did not want to sell the land, so
an agreement was made. Mr. Guymon would have the grazing rights to the
edge of the water. The BLM did not like this, so they stepped in and did
not allow Mr. Guymon to graze next to the water. Norman Nielson was sent
to tell Mr. Guymon the news. He did not like this, but there was nothing
he could do about it. The land was appraised at $500 an acre. Mr. Guymon
was paid $16,000 for his land. (Watkins)
 |
| Recapture Dam with part of the reservoir. The Recapture Dam
was started in 1982 and by 1985 the dam was dedicated. The total cost was
$7.8 million. The dam holds 9,000 acre ft. The dam was built for irrigation.
A pipe runs from the bottom of the dam to the farms for irrigation. - Photo
taken by Kristina Long, 1997. |
Three Phases to Complete Recapture Dam
The dam could now be started. It was built in three phases. The first phase
was to form a good solid base costing $1.2 million. The second phase began
in 1983. It was to build a coffer dam to hold water so the actual dam could
be built and to help build the dam. It cost $1.5 million. In 1984 the third
and final phase began. The actual dam was begun. In 1985 the dam was finished
and dedicated. The total cost was $7.8 million. The dam was built with
the purpose in mind for irrigation. A pipe was run from the bottom of the
dam to the farms for irrigation. Pressure became better and more people
could irrigate. The dam holds 9,000 acre ft. The city owns 500 acre ft.
a year, at a cost of $20,000 a year. (Shumway. 3-4.)
Old and New Pipelines
Before the tunnel was built, the first pipelines were put in. They were
6 inch pipes made out of 2 inch strips of redwood hooked together and wrapped
every so often with wire. The trenches were dug and the pipe was laid.
The cost of the pipes and the first reservoir was $45,000. All the families
that used the wooden pipes had to dig the trench to their houses. Each
tap and hydrant they had cost $1.50.
 |
Blue Mountain, the source of Blanding's main water supply.
- Photo taken by Kristina Long, 1997. |
On August 19, 1947, the town of Blanding voted to put in a pipeline
to carry water from Blue Mountain to Blanding. It was contracted by Douglas
Harvey. The trench was then cut in the mountain and the pipe was laid.
It cost $139,992.39. (Perkins, Nielson, Jones 165-168.) Most of the old
pipelines are galvanized. When they have to be replaced, they are replaced
with plastic called poly ethylene. It is a high density plastic. It is
different from PVC. The new pipes have a longer life expectancy and come
in rolls. There are no joints. One problem with this is that pipes can't
be found with a metal detector so a map with good information is needed.
Some big improvements were made in the culinary water system just recently.
New pipes were installed to improve fire protection and increase water
pressure. A lot of 2 inch pipes were replaced mostly with 6-inch. There
was 21,000 feet of 6-inch, 8,000 feet of 8-inch, and 11,000 feet of 10-inch
installed. New pipes were installed along the highway north and south of
town. The bid was just less than $570,000.
Recapture Dam Receives Pipelines
When Recapture Dam was built, the city had no way of getting their 500
acre feet of water, so they sold it back to the Irrigation Company. Because
of the drought the city recently put in a pipe line so this water could
be used. It hooks onto the irrigation line which starts just below Parley
Hurst's field. It uses 12 inch pipes, then it comes to a pumping station
and hooks into 8-inch pipe then into 10 then to 12 and finally 18 inch
near the water treatment plant. This line can be used for irrigation also.
The bid was just less than $500,000. (Philip Palmer, interview.)
Over the years Blanding has gone through some tough times but they have
found new resources and were able to sustain themselves. The problem isn't
over. Additional water will always be needed to this arid southeastern
Utah town.
Casey Black wrote this paper while he attended San Juan
High School as a junior, in 1991.
Works Cited:
Palmer, Philip. Interviewed by Casey Black, January 13, 1991, Blanding
UT
Perkins, Cornelia A. and Marian G. Nielson, and Lonora B. Jones, Saga
of San Juan, San Juan County Daughters of Utah Pioneers, 1957
Shumway, Preston. " Water Development in Blanding" San Juan High
School.
Watkins, Ivan. Interviewed by Harley Watkins, San Juan County, Utah, November
12, 1987
Return to Table of Contents
Last Updated July 11, 1997 by Janet
Wilcox